Install, fill and run the receiving vessels before anything is moved in. Each vessel should be filled, allowed to settle, and monitored long enough to confirm it is holding temperature and using nitrogen at the normal rate. A vessel that is consuming far more than expected should be investigated before it is trusted with samples.
At the same time, confirm that alarms and remote monitoring are live and tested, that liquid nitrogen supply is in place, whether bulk or from a self pressurising dispenser, and that the room has been assessed with our oxygen depletion calculator and fitted with oxygen monitoring. Check that the internal layout of each vessel matches the canisters and goblets being moved.
If the old store was close to full, a move is the natural time to add capacity with vessels such as the CryoNest XL or CryoNest XXL. A service visit at the new site gives a baseline. See the full plan in relocating an IVF cryostore.